Corrective Maintenance Actions in Replacing Broken Electric Motor Shafts Due to Overload in the Separator Machine at PT. Hutahaean

Authors

  • Karti Karti Politeknik Teknologi Kimia Industri Medan
  • Geo Peterson Nainggolan Politeknik Teknologi Kimia Industri Medan

DOI:

https://doi.org/10.56862/irajtma.v3i3.159

Keywords:

Corrective Maintenance, Motor Shaft, Machine Maintenance, Separator.

Abstract

This research discusses the replacement of a broken motor shaft due to overload as a Corrective Maintenance action on the separator unit at PT. Hutahaean, Tapioca Factory. The objective of this research is to understand the Standard Operating Procedure (SOP) for replacing a broken motor shaft and to apply preventive steps to avoid further damage to the electric motor in the separator unit. The electric motor plays a crucial role in driving the separator machine, especially in the separation process of tapioca starch. Overloading led to the breakage of the motor shaft, disrupting the production flow. This study demonstrates that effective Corrective Maintenance can restore the machine's optimal function and reduce production downtime. The findings also highlight the importance of routine maintenance of machine components to prevent future severe damages.

References

Agustina, S., dan N. Nugroho. 2015. "Analisa Motor DC (Direct Current) sebagai Penggerak Mobil Listrik." Jurnal Mikrotiga 2 (1).

Adlie, Taufan Arif, Fazri Amir, dan Widi Elfianto. 2015. “Perancangan dan Pembuatan Mata Pisau Perajang Singkong Tipe Vertikal.” JURUTERA-Jurnal Umum Teknik Terapan 2 (01): 19–26.

Kurniawan, Fajar. 2013. Manajemen Perawatan Industri. Yogyakarta: Graha Ilmu.

Mott, Robert L. 2009. Elemen-Elemen Mesin dalam Perancangan Mekanis. Yogyakarta: Andi.

Ngadiyono, Yatin. 2010. Pemeliharaan Mekanik Industri. Yogyakarta: Universitas Negeri Yogyakarta.

Parsa, I. Made. 2018. Motor-Motor Listrik. Kupang: Universitas Nusa Cendana.

Silitonga, A. Sumadi, dan Nelson Silitonga. 2023. “Pengaruh Penurunan Kecepatan Elektromotor untuk Menggerakkan Bowl Separator terhadap Kinerja Separator di Pabrik Tapioka PT Hutahaean.” IRA Jurnal Teknik Mesin dan Aplikasinya (IRAJTMA) 2 (1): 51–57. https://doi.org/10.56862/irajtma.v2i1.45.

Sularso, K. S. 2002. Dasar Perencanaan dan Pemilihan Elemen Mesin. Edisi ke-10. Jakarta: PT Pradnya Paramita.

Tambunan, Bayu Hillam Saputra, dan Karti Karti. 2023. “Studi Kasus: Dampak Panjang Kabel Penghantar terhadap Drop Tegangan dalam Distribusi Daya dari Generator ke Motor Induksi 3 Fasa di Unit Screw Press PTP Nusantara II Sawit Hulu.” IRA Jurnal Teknik Mesin dan Aplikasinya (IRAJTMA) 2 (3): 15–21. https://doi.org/10.56862/irajtma.v2i3.71.

Yogatama, Prasojo, dkk. 2022. "Perancangan Poros, Pulley, dan V-Belt pada Sepeda Motor Honda Beat FI 2014." Jurnal Wahana Pendidikan 8 (17): 373–383.

Published

2024-12-30

How to Cite

Karti, K., & Nainggolan, G. P. . (2024). Corrective Maintenance Actions in Replacing Broken Electric Motor Shafts Due to Overload in the Separator Machine at PT. Hutahaean. IRA Jurnal Teknik Mesin Dan Aplikasinya (IRAJTMA), 3(3), 51–57. https://doi.org/10.56862/irajtma.v3i3.159

Issue

Section

Scientific Article